21 activities
DescriptionDurationStartFinishType
Design
Construction
NTP to GC for Site & Foundation
—Feb 2, 2026—Start MS
Foundations
45dFeb 2, 2026Apr 3, 2026Task
Framing & Exterior Closure
80dApr 6, 2026Jul 24, 2026Task
MEP & Interior
200dMay 4, 2026Feb 5, 2027Task
Substantial Completion
——Feb 5, 2027Finish MS
Cx & Owner Acceptance
50dFeb 8, 2027Apr 16, 2027Task
Buyer Payment Milestones
DescriptionAmount
Lot Cost
$895,000
General Contractor Costs
$0
GC Hard Cost
$0
GC Soft Costs
$0
Developer Fees
$0
Soft Costs + Reserves
$0