| Description | Duration | Start | Finish | Type |
|---|---|---|---|---|
Design | ||||
Construction | ||||
NTP to GC for Site & Foundation | — | Aug 13, 2025 | — | Start MS |
Foundations | 15d | Aug 13, 2025 | Sep 2, 2025 | Task |
Framing & Exterior Closure | 75d | Sep 3, 2025 | Dec 16, 2025 | Task |
MEP & Interior | 120d | Oct 1, 2025 | Mar 17, 2026 | Task |
Substantial Completion | — | — | Mar 17, 2026 | Finish MS |
Cx & Owner Acceptance | 30d | Mar 18, 2026 | Apr 28, 2026 | Task |
Buyer Payment Milestones | ||||
| Description | Amount |
|---|---|
Lot Cost | $995,000 |
General Contractor Costs | $0 |
GC Hard Cost | $0 |
GC Soft Costs | $0 |
Developer Fees | $0 |
Soft Costs + Reserves | $0 |
| Total Estimated Cost | $995,000 |