Lot PG-7

Paddock
Paddock GarageTBD
18 activities
DescriptionDurationStartFinishType
Design
Construction
NTP to GC for Site & Foundation
—Aug 13, 2025—Start MS
Foundations
15dAug 13, 2025Sep 2, 2025Task
Framing & Exterior Closure
75dSep 3, 2025Dec 16, 2025Task
MEP & Interior
120dOct 1, 2025Mar 17, 2026Task
Substantial Completion
——Mar 17, 2026Finish MS
Cx & Owner Acceptance
30dMar 18, 2026Apr 28, 2026Task